Skip to content

Search website by keyword

Business at YYJ

← Back to all Projects

Lower Passenger Departure Lounge Expansion

Lower Passenger Departure Lounge Expansion
Total Est. Cost:  $19.4M
Completion:  This project is currently underway with completion anticipated for the Spring of 2020.

In response to growth in passenger traffic, up-gauging of aircraft and the need to improve the safe operation of the apron and hold room, work was approved to create a building addition to meet a new state of operations.  The LHRX projects is a 1765m2 addition to the lower passenger departure lounge creating space to accommodate all ground load passenger traffic for the next decade and beyond including the addition of another gate position.

Principle drivers include:  improving operational safety and efficiency for hold room operations; providing sufficient ground load capacity for both seating and serving passengers now and into the future; provide sufficient floorplate to allow additional revenue opportunities with the space.

Design features and amenities will include:

  • Minimizing walking distances to aircraft;
  • covered walkways on aprons;
  • segregated gates with a one-podium, one-door, one-aircraft principle;
  • improved ground equipment storage;
  • new premium washroom facilities including pet relief for service animals and universal;
  • family room;
  • expanded food and beverage and additional retail; and
  • basement.

Significant Developments: The focus for the past four weeks was geared broadly at all trades.  The following is a summary of the key milestones to November 27,2019:  

Phase (1) One - Complete

  • Occupancy was granted on the new expanded lower passenger departure lounge and Go-Live was achieved the morning of September 19, 2019.  This completes Phase One.
Phase (2) Two
  • Deficiency clean-up for Lower Passenger Departure Lounge main floor
  • Concrete foundations and formwork for Phase 2 basement and main floor
  • Backfilling and rough-in for slab on grade
  • Demolition of floor slab and tree wells on the west side of the old passenger departure lounge area (future open seating area)
  • Cladding on the wall between the existing and new rooflines
  • Prep work for completing the art wall at the south end of the old passenger departure lounge
  • Complete concrete upstand walls and elevator pit including damp-proofing
  • Perimeter drains and backfill around elevator shaft
  • Concrete foundation work for the west canopy

Schedule: The project commenced on January 15, 2018.  There are 3 primary phases of work associated with this project.  The first phase being the main lower passenger departure lounge expansion to the north over 19 months.  Phase One was completed September 19, 2019. Phase Two involves the new washroom block and vertical circulation core to the basement over seven months.  Phase three includes renovations to the existing passenger departure lounge and is anticipated to take one month.  The total project is expected to be completed by Spring 2020.

Below is a time-lapse video of the last week of the construction project.  You can view previous weeks' videos on YouTube here and more progress pictures in our Photo Gallery.