Skip to content

Search website by keyword

Business at YYJ

← Back to all Projects

Extend Taxiway Echo East

Extend Taxiway Echo East 2019
Total Est. Cost:  $4.3M
Construction Start Date:  June 2019
Completion:  November 2019

Taxiway Echo is the parallel taxiway serving Runway 09-27, the main runway used for commercial operations.  The 2012 Master Plan identified extending this taxiway to the threshold of Runway 27 as a key operational project to complete.

The successful contractor for this project is C-1 Contractors.  The contractor has mobilized and site excavation is underway.  Construction will take place over the summer months with completion by the end of October. 

The following is a summary of the key milestones to October 31, 2019:  

  • Installation of sub-base material is complete
  • Base material installation is complete
  • Tie-in to threshold of Runway 27 complete including asphalt
  • All drainage, lighting and signage rough-ins are complete with finishing work to occur once paving complete