Airside Pavements 2020

Airside Pavements 2019
Budget:  $1.5M
Project Start:  Summer 2020
Completion:  December 2020

Victoria Airport Authority (VAA) has an ongoing pavement restoration and rehabilitation program to ensure safe aircraft operations on VAA aircraft maneuvering surfaces.  This years activities will primarily be directed towards taxiway restorations.

The scope of this project has been reduced to complete critical work only.  Detailed design is underway.  Tender will be issued in early May with a late May award.  Paving work will take place over the summer.