Skip to content

Search website by keyword

Business at YYJ

Projects & Planning

  • Lower Passenger Departure Lounge Expansion

    Lower Passenger Departure Lounge Expansion

    Lower Passenger Departure Lounge Expansion
    Total Est. Cost:  $19.4M
    Completion:  This project is currently underway with completion anticipated for the Spring of 2020.

    In response to growth in passenger traffic, up-gauging of aircraft and the need to improve the safe operation of the apron and hold room, work was approved to create a building addition to meet a new state of operations.  The LHRX projects is a 1765m2 addition to the lower passenger departure lounge creating space to accommodate all ground load passenger traffic for the next decade and beyond including the addition of another gate position.

    Principle drivers include:  improving operational safety and efficiency for hold room operations; providing sufficient ground load capacity for both seating and serving passengers now and into the future; provide sufficient floorplate to allow additional revenue opportunities with the space.

    Design features and amenities will include:

    • Minimizing walking distances to aircraft;
    • covered walkways on aprons;
    • segregated gates with a one-podium, one-door, one-aircraft principle;
    • improved ground equipment storage;
    • new premium washroom facilities including pet relief for service animals and universal;
    • family room;
    • expanded food and beverage and additional retail; and
    • basement.

    Significant Developments: The focus for the past four weeks was geared broadly at all trades.  The following is a summary of the key milestones to November 27,2019:  

    Phase (1) One - Complete

    • Occupancy was granted on the new expanded lower passenger departure lounge and Go-Live was achieved the morning of September 19, 2019.  This completes Phase One.
    Phase (2) Two
    • Deficiency clean-up for Lower Passenger Departure Lounge main floor
    • Concrete foundations and formwork for Phase 2 basement and main floor
    • Backfilling and rough-in for slab on grade
    • Demolition of floor slab and tree wells on the west side of the old passenger departure lounge area (future open seating area)
    • Cladding on the wall between the existing and new rooflines
    • Prep work for completing the art wall at the south end of the old passenger departure lounge
    • Complete concrete upstand walls and elevator pit including damp-proofing
    • Perimeter drains and backfill around elevator shaft
    • Concrete foundation work for the west canopy

    Schedule: The project commenced on January 15, 2018.  There are 3 primary phases of work associated with this project.  The first phase being the main lower passenger departure lounge expansion to the north over 19 months.  Phase One was completed September 19, 2019. Phase Two involves the new washroom block and vertical circulation core to the basement over seven months.  Phase three includes renovations to the existing passenger departure lounge and is anticipated to take one month.  The total project is expected to be completed by Spring 2020.

    Below is a time-lapse video of the last week of the construction project.  You can view previous weeks' videos on YouTube here and more progress pictures in our Photo Gallery.

     

     

  • Parking Improvements

    Parking Improvements

    Parking Improvements 2018
    Total Est. Cost:  $6.2M
    Status:  Substantially Complete

    This project created approximately 525 new long term parking stalls, with a future toll plaza, in the area of open field immediately south of the car rental service facility, adjacent to the roundabout. The scope of work includes linking the three existing gravel overflow lots to the new lot in a manner that allows a single pay transaction location. Improved lighting for the overflow lots and appropriate pedestrian access to the ATB from the new lot will be part of the work as well.

    This 500+ space expansion provides adequate capacity to absorb the overflow parking that is currently occurring into the gravel overflow lots formalizing this activity as permanent. It will be constructed with the infrastructure to operate a future toll plaza similar to the existing that offers pay on exit either through a kiosk or staffed booth. Natural growth will eventually fill the new permanent spots with the gravel lots continuing to provide overflow capacity now and into the future. The lot is designed to support a future shuttle operation.

    The three adjacent gravel overflow lots will be linked with this new lot in such a way that the toll plaza area becomes both the way in and the way out to all four lots. This will afford an opportunity to capture 100% of the revenues associated with the overflow parking. Currently over 660 stalls of the approximately 2380 available parking spaces are uncontrolled stalls in the four overflow lots. This represents nearly 28% of available parking capacity.

    The project will see the installation of lighting and CCTV in both the new and the overflow lots to improve the overall safety and security of the parking operation. The lamp standards and bases will be the relocatable type allowing them to move in the future as the gravel lots are reconfigured..

    The design incorporates rain garden technology for the management of storm water flows and filtration of the waters collected. There will be 6 designated electric vehicle charging spaces to carry on the program started in both the long and short term lots in 2015.

    Significant Developments:  This project is substantially complete.  Installation of a power kiosk to support new signage at the entrance to the long term and short term lots is underway.  100% of the lot has been paved and is fully available to meet any overflow demand.  The pay booth is in service.

     

  • Terminal Precinct Pavements

    Terminal Precinct Pavements

    Terminal Precinct Pavements
    Total Est. Cost:  $1.9M
    Completion:  October 2018
    Status:  Complete 

    This project involves resurfacing the main Victoria Airport Authority (VAA) road network, from the East Saanich roundabout to the front of the ATB and then back out towards the Willingdon Road roundabout. It also includes drainage improvements and resurfacing of the central portion of the long term parking lot. Updated lighting in all areas will be a part of the project.

    Willingdon Road from the East Saanich Road roundabout was last resurfaced over 20 years ago. The road is experiencing rutting in both lanes for most of its length. There are also load related failures evident at numerous locations. An ongoing program of patching has taken place over the last 10 years to maintain the surface. A 2013 condition survey recommended restoration of the full surface within a 5 year horizon.

    Electra Boulevard, the air terminal building access and frontage road, was last resurfaced in 2007 and is exhibiting failures ranging from minor cracking to multiple areas of load related failure. Resurfacing the whole road rather than a multi-year program of patching is the preferred approach given the operational challenges associated completing work on this very busy road.

    The central portion of the long term parking lot was constructed and last resurfaced in 1987 and is exhibiting significant areas of age and load related failure. This is particularly evident in the driving lanes at the entry at the north end of the lot. The short term lot, which was originally constructed at a similar time as the long term lot, was fully resurfaced in 2011.

    As part of this project all the lighting in the long and short term lots as well as along Willingdon Road will be upgraded to LED fixtures. The parking lot fixtures will feature energy saving controls to reduce energy consumption.

     

  • Apron IV Expansion - Phase 4A

    Apron IV Expansion - Phase 4A

    Apron IV Expansion - Phase 4A 2019
    Total Est. Cost:  $7.1M
    Construction Start Date:  May 2019
    Completion:  December 2019

    Apron IV is the apron utilized for air carrier operations at the Air Terminal Building (ATB).  Identified as a key component in the 2012 Master Plan as well as the 2014 Terminal Precinct Plan, this apron expansion will expand the parking stands available on the west side of the apron and is necessary to accommodate the next phase of ATB expansion to the west.

    Detailed design for this project is complete. The project went out to tender by invitation and the successful proponent was Kinetic Construction.

    The following is a summary of the key milestones to November 27, 2019:  

    • All excavation is now complete
    • Installation of storm water drain piping and electrical piping installation is complete.  Waiting on a small pump station to arrive so glycol collection  system can be completed.  The station is scheduled to arrive November 29th
    • Two of three lamp standards are installed, the final pole arrives November 29th
    • All of the machine and hand placed concrete has now been installed
    • Sawcutting and joint sealing for the concrete panels started November 18th
    • Paving started November 21st
    • Viewing area construction is underway

  • Extend Taxiway Echo East

    Extend Taxiway Echo East

    Extend Taxiway Echo East 2019
    Total Est. Cost:  $4.3M
    Construction Start Date:  June 2019
    Completion:  December 2019

    Taxiway Echo is the parallel taxiway serving Runway 09-27, the main runway used for commercial operations.  The 2012 Master Plan identified extending this taxiway to the threshold of Runway 27 as a key operational project to complete.

    The successful contractor for this project is C-1 Contractors.  The contractor has mobilized and site excavation is underway.  Construction will take place over the summer months with completion by the end of October. 

    The following is a summary of the key milestones to November 27, 2019:  

    • Taxiway paving is complete - there are two small associated driveway stubs to complete
    • Finish grading is underway since asphalt is complete
    • Line painting is scheduled
    • Taxiway lighting and signage installations are complete
    • Final grading of shoulders is underway

  • Automated Exit Lane Portals

    Automated Exit Lane Portals

    Automated Exit Lane Portals 2019
    Total Est. Cost:  $425K
    Completion:  December 2019

    This project will see the installation of an engineered solution to remove the 24/7 security staffing requirement at the exit from the passenger departure lounge.  The solution includes two one-way tunnels that allows arriving passengers free egress in one direction from the lounge but will lock down upon detection of movement in the wrong direction.

    This project is in the planning and procurement phase.  Work is underway with the architect on the related work surrounding the door system.  The door system was originally anticipated to arrive late July but will now be arriving by the end of September with installation to follow.

    The following is a summary of the key milestones to November 27, 2019

    The work is now substantially complete.

  • Acquire ARFF Vehicle

    Acquire ARFF Vehicle

    Acquire ARFF Vehicle 2019
    Total Est. Cost:  $1.1M
    Start Date:  March 2019
    Completion:  October 2020

    This project will acquire a medium sized Aircraft Rescue Fire Fighting (ARFF) vehicle to provide a second front line vehicle when one of the large ARFF vehicles is out of service.

    Drafting of specifications and the Request for Proposal (RFP) documents is complete.  The RFP was sent to the top three suppliers in North America.  The RFP closed May 31, 2019 and Rosenbauer America was the successful proponent.

    These vehicles have a very long lead time - estimated to be between 14 and 16 months.  An order mid-year 2019 would see the vehicle delivered towards the end of 2010. 

     

  • Airside Fleet Renewal

    Airside Fleet Renewal

    Airside Fleet Renewal 2019
    Total Est. Cost:  $850K
    Construction Start Date:  April 2019
    Completion:  December 2019

    This project is aimed at the procurement of a new truck and anti/de-icing product applicator as well as a high speed broom attachment for the Larue multi-purpose vehicle.  The truck and applicator are replacements for existing equipment and the sweeper is an incremental add to the airside operations fleet.

    The Request for Proposal (RFP) for the truck and applicator is completed was posted in early May.  

    • The broom attachment has arrived and training on its use will start July 30th
    • The applicator contract was awarded to Team Eagle Ltd., a Canadian airport-specific equipment supplier
      • The until is in manufacturing and will be delivered late September/early October
    • The truck contract has been awarded to P&R Truck Centre, a Vancouver Island company.
      • The unit is a Western Star
      • Delivery is anticipated in December