Skip to content

Search website by keyword

About YYJ

Photo Gallery

Apron IV Expansion (2015/16) - Phase 1

September 1 - Apron IV Expansion underway.
September 1 - Apron IV Expansion underway.

September 1- View of Apron IV Phase 1 Expansion from work site looking south towards air terminal building.
September 1- View of Apron IV Phase 1 Expansion from work site looking south towards air terminal building.

September 1 - Looking west from the end of the hauling road to work site.
September 1 - Looking west from the end of the hauling road to work site.

September 1 - WestJet taxiing past construction along Apron IV.
September 1 - WestJet taxiing past construction along Apron IV.

September 3 - Rooftop view of early days of construction on Apron IV Expansion.  The recent rain creating a challenging situation for the gravel trucks.
September 3 - Rooftop view of early days of construction on Apron IV Expansion. The recent rain creating a challenging situation for the gravel trucks.

September 16, 2015
September 16, 2015

September 16, 2015
September 16, 2015

September 16, 2015
September 16, 2015

September 25 - Progress continues.   Excavation is nearing completion.  Next is preparation and framing for a concrete pour.
September 25 - Progress continues. Excavation is nearing completion. Next is preparation and framing for a concrete pour.

September 25 - Progress continues.   Excavation is nearing completion.  Next is preparation and framing for a concrete pour.
September 25 - Progress continues. Excavation is nearing completion. Next is preparation and framing for a concrete pour.

September 25 - Progress continues.   Excavation is nearing completion.  Next is preparation and framing for a concrete pour.
September 25 - Progress continues. Excavation is nearing completion. Next is preparation and framing for a concrete pour.

September 30 - Drainage work.
September 30 - Drainage work.

September 30 - Beginning of concrete pour for one of the aircraft parking stands.
September 30 - Beginning of concrete pour for one of the aircraft parking stands.

September 30 - Concrete pour.
September 30 - Concrete pour.

September - Completed concrete pour for one of the aircraft parking stands.
September - Completed concrete pour for one of the aircraft parking stands.

October - Progress Photo
October - Progress Photo

October - Progress Photo
October - Progress Photo

October - Progress Photo
October - Progress Photo

October - Progress Photo
October - Progress Photo

October - Progress Photo
October - Progress Photo

November - Progress Photo.
November - Progress Photo.

November - Progress Photo.
November - Progress Photo.

November - Progress Photo.
November - Progress Photo.

November - Progress  Photo.
November - Progress Photo.

November - Progress Photo.
November - Progress Photo.

November - Progress Photo.
November - Progress Photo.

November - Progress Photo.
November - Progress Photo.

November - Progress Photo.
November - Progress Photo.

December - Progress Photo
December - Progress Photo

December - Progress Photo
December - Progress Photo

December - Progress Photo
December - Progress Photo

December - Progress Photo
December - Progress Photo

December - Progress Photo
December - Progress Photo

December - Progress Photo
December - Progress Photo

December - Progress Photo
December - Progress Photo

December - Progress Photo
December - Progress Photo

December - Progress Photo
December - Progress Photo

December - Progress Photo
December - Progress Photo

December - Progress Photo
December - Progress Photo

January - Progress Photo
January - Progress Photo

January - Progress Photo
January - Progress Photo

January - Progress Photo
January - Progress Photo

January - Progress Photo
January - Progress Photo

January - Progress Photo
January - Progress Photo

February Progress - Paving work continues with the improvement in the weather.  Additional lifts of asphalt are poured.
February Progress - Paving work continues with the improvement in the weather. Additional lifts of asphalt are poured.

February Progress - Paving work continues with the improvement in the weather.  Additional lifts of asphalt are poured.
February Progress - Paving work continues with the improvement in the weather. Additional lifts of asphalt are poured.

February Progress - Paving work continues with the improvement in the weather.  Additional lifts of asphalt are poured.
February Progress - Paving work continues with the improvement in the weather. Additional lifts of asphalt are poured.

February Progress - Paving work continues with the improvement in the weather.  Additional lifts of asphalt are poured.
February Progress - Paving work continues with the improvement in the weather. Additional lifts of asphalt are poured.

February Progress - Paving work continues with the improvement in the weather.  Additional lifts of asphalt are poured.
February Progress - Paving work continues with the improvement in the weather. Additional lifts of asphalt are poured.

February Progress - Paving work continues with the improvement in the weather.  Additional lifts of asphalt are poured.
February Progress - Paving work continues with the improvement in the weather. Additional lifts of asphalt are poured.

March - Progress photo.
March - Progress photo.

March - Progress photo.
March - Progress photo.

March - Progress photo.
March - Progress photo.

March - Progress photo.
March - Progress photo.

March - Progress Photo
March - Progress Photo

March - Progress Photo
March - Progress Photo

March - Progress Photo
March - Progress Photo

March - Progress Photo
March - Progress Photo

March - Progress Photo
March - Progress Photo

March - Progress Photo
March - Progress Photo

March - Progress Photo
March - Progress Photo

March - Progress Photo
March - Progress Photo

April - Progress Photo
April - Progress Photo

April - Progress Photo
April - Progress Photo

April - Progress Photo
April - Progress Photo

April - Progress Photo
April - Progress Photo

April - Progress Photo
April - Progress Photo

April - Progress Photo
April - Progress Photo

April - Progress Photo
April - Progress Photo

May - All but line painting complete.  See Phase 2 for more photos.
May - All but line painting complete. See Phase 2 for more photos.